Loft extension build diary - page 6
Page1 : Page2 : Page3 : Page4 : Page5 : Page6 : Page7
 
 
   

 

 

 


Previous page here
 Week 11  14/05/07 - 20/05/07
7 weeks over

 

14th May - Wahey! The scaffolding's gone!

Came home to find the letters worked - the scaffolding has gone! I'm pleased about this as it knocks out one of the items of grief - he has his property back and won't be getting arsey over it.
 

The old floorboards, now cut up so much they're useless and need replacing.

This evening I looked up the prices of loft floorboards, they're about £10 for one which is 1m x 3m... nowhere near £400 then as the MD stated a month ago (click). Seems my instincts back then were right.. 

 
This is how it's supposed to be.
 
Tomorrow they'll finish the insulation and the flooring. I've asked them to then move onto the electrics, or at least connect a light switch up to the landing lights that have no way to turn off!

This, and 2 other bulbs (rear of pic) have been burning for at least 4 weeks now!!

   

 

 

15th May - This isn't a loft extension, this is a soap opera!

 

At about 3pm I got an email containing a copy of a letter that was due to arrive today. The letter was.. well... bizarre.

It seemed to be written by someone who was completely detached from this job.

 

   
 


The first thing I thought of when reading it was Mohammed Saeed al-Sahaf, the Iraqi Minister of Information:

"There is no problem with this loft"
"We are almost there"
"There is only 1 day of work left"

 

 
 

I think the best way to show this is to show the entire letter below on the left, along with my comments on the right, but be warned... it's starting to get catty...

 

   
  Thank you for your e-mail dated 11 May 2007.
 


Firstly, I would like to make it clear that we were not being clever with the scaffold not coming down. Please be assured we want to get the job completed as soon as possible. Also, the reason that I have not signed for the recorded delivery of your e-mails is that I have not received them.
 

That's the move your scaffolding email (click).. or is it the update?

 

Errr.... "we were not being clever with the scaffolding not coming down"  and "the reason that I have not signed for the recorded delivery"... Well, that sounds like a direct reply to my update of 11th May Click. (I'll ignore the fact that there is recorded delivery of post, not email and that there is no recorded delivery of email.)

So this is interesting, so does this mean that the company have found my blog? If they have, does that matter? Are they trying to deny that they used the threat of leaving the scaffolding up as blackmail? That's odd - particularly as he left a recorded message on my machine and told me he was recording it as well.

 

 
  I have spoken to the Managing Director of the scaffold company who says that not taking it down was an oversight on his part. They were called off the job to attend an emergency and have not been back. He assures me, however, that it is coming down today.
 
Right, so about the "I will not take the scaffolding down" voice message? Or have you had a sudden change of heart and decided to take it down anyway, without any communication or negotiation.

Hmmm.. so are you reading this?

 
  From the outset of this contract I have to say that you have proved unreasonable in all dealings and we were surprised we got the contract because you have not treated us as such. Ignoring the fact the sentence is poorly constructed, the only way I can interpret this is as a personal insult. I don't agree that I've been unreasonable at all, far from it. This diary of events shows that I tried to be reasonable with my communications and time, setting deadlines and allowing them to slip.

I really don't know what he means by saying he was surprised he got the contract.

 

 
  You have repeatedly ignored my calls and messages and just continued to send me e-mails. I would like to make the following points:
 

 

This is not true. I have ignored just two calls of his, once on 17th April where he asked me to have a conference call with him and his salesmen to discuss the "3-4 weeks" sales time (click) and once on the 1st May where he acknowledged he was off the job (click).

Oh, and he was more than happy to receive confirmation of the order by email....

 

 
  1. The contract states that lofts take an average of five-six weeks to complete, however no specific time is guaranteed. No completion date has been given to you either verbally or in writing. The contract (I've had a look at the document received by post) states 4-5 weeks, okay, so not the 3-4 weeks quoted by the salesman, but if that isn't a specific time then what is? His salesman came round to my house and convinced me that they could do it in 3 - 4 weeks and did this by explaining how (with no subcontractors, using specialist teams, etc..). Yes no completion date was given, but the "4-5" weeks on the contract would pretty reasonably imply 5 weeks should be the maximum time.. and as we're on week 12 and still going, one could argue that perhaps that salesman had made promises that weren't intended to be delivered merely to get the sale?

No, no completion date was initially given to me, but despite asking, and asking and asking (for example, click), I forced the issue and agreed one with the Project Manager and, as agreed, put it in writing (click). I also discussed it with the Managing Director personally at my house on 10th April (click). I then confirmed again, by recorded delivery on 16th April that he had agreed to this date (click) and his emailed reply on the 17th April (click) confirms that he acknowledged this date and confirmed dates it would be completed. This date slipped twice without any solid reason.

 

 
  Due to unforeseen occurrence, i.e., the plumber leaving your job Tuesday morning due to family emergency and not returning until Friday, things have taken longer than you expected. As he did the 1st fix, it is sensible for him to come back and do the 2nd fix. Umm, the plumber left on Wednesday because he couldn't find the hot and cold feed, nor the radiator pickup. The plumber that did the first fix did not come back to do the second fix, someone else did.. and he was the chap who left on Wednesday. The person who came on Friday was a different plumber who found the hot/cold pickups and left (leaving the remainder of the plumbing work undone).

 

 
  However, the biggest delay was that you claimed your insulation was not correct. We waited approximately 5 days for the Building Surveyor to come to re-check something he had already passed. I myself met with you at 6.30am one Monday morning to look at the problem. While there I found out the Inspector had photos and had passed the floor. The only part of the floor not done at the time was the bathroom as the plumber has requested it not be laid while he laid his pipes. At this meeting you were showed the insulation and shown you were wrong. Why are you now stating it is not there?

 

Oh not the building inspector and the fire protected floor AGAIN?!

This is precisely why I have been putting things in writing, rather than phone calls that seem afterwards to have not taken place. I put this point in writing to him on 4th May (click), writing that a) the building inspector has not been round, b) the insulation under the floorboards has not been signed off, and c) his (intimidating) visit opened only a hole in across one area that had "luckily" had a strip of insulation under it.

Let me explain with a picture:

What does he think I did, remove this horrible material that has no value, take up the chicken wire, remove any evidence of it ever being there, destroy the floorboards and pay these guys extra labour just to be able to take this picture?? No, the fact is we didn't look under there. I'm not  a building inspector and not qualified to know what to look for. He is, did and found this.

Anyway it would be really pedantic to say that he never came at 6:30am on a Monday as it was 7:30 on Tuesday (click).

 

 
  2. You, with Frank, changed the design of the windows on site, which i.e. subsequently ordered. I have spoken to the Building Inspector who said it was a passing comment only, and he was going to check if there was a problem. If these need changing, it will be at your cost, as you changed these from the ones on plan. Oh, now that is a low shot!

When the salesman turned up, we said we wanted these window doors. He showed us pictures of these types of doors so we selected, and guess what? They're confirmed in writing on the contract. Quote "One UPVC window 1100m x 1250mm will be fitted to the top of the staircase, and a set of 4 panel French Doors with Juliette balcony to the bedroom.". When the plans turned up on the 6th March showing it as incorrect, we immediately brought this to his attention (click) and he agreed that there had been a disconnect between sales and drawing and thought it was best to get the architect back in. This was supposed to happen on the 8th, then the  9th, then 12th March before saying "it's okay, we'll just do it and it's too late for the architect to come back in now".

So, basically we got the windows that the salesman sold, that we wanted and that was confirmed in the order, but he's claiming we changed them...! Eh?

 

 
  3. The balcony has been installed correctly and according to building regulations. The floor guard is there for safety reasons. It has been added by the outside Company that installed it as a safety measure due to concerns many Councils have with the gap. I can confirm it is a Juliet Balcony. Another strange area.

This letter came in on 15th May and here he refers to a point in which he spoke to the building inspector on the 8th May (click) so he knows perfectly well what the situation is. This is so strange; I've told him I'm speaking directly to the building inspector but he's coming back as if I'm really stupid.

The building inspector said the width was too big and it needed to be shortened. Full stop. No compromise. Has to be done to be compliant. I don't care if he confirms it's a doughnut made from recycled Kryptonite, it's not compliant!

 

 
  4. The bulkhead above the stairs can be cut back and redone. However, again you changed this as you requested it to be levelled off. I believe the height is 1.85m from the step which is normally quite sufficient to be passed. He's getting confused between the bulkhead of the new landing ceiling (which was awful and I requested they make it reasonable) and bulkhead under the new bathroom floor that does not provide sufficient head height.

This is the same as before - he spoke about this specific point in his phone call with the building inspector on the 8th May where he was told the height HAS to be 2.0 (or higher) and it's 1.85m. So why, oh why oh why would he be telling me the height (which is 1.85) and it's normally sufficient to be passed?

 

 
  5. As regards you contractor, Pete, he is giving you false information and running our staff down. If he is so good, why did you not give him the contract?

 

Well that's not much of an argument is it? Why is he giving me false information? All he's done is: come in, met with the building inspector, and performed the works that the inspector has said he requires for compliance. He hasn't yet got to finishing off the bits that weren't finished.

Why didn't I give him the contract? Oh, that's an easy one... because they said they could do it in 3 - 4 weeks and Pete said 10 - 12 weeks. They said their firm had many craftsmen that had worked for them for years and were specialist as they only did lofts. Multiple people hitting it all at once in a quality, seamless team.

Yeah, I feel a mug now!

 

 
  6. When we turned up to complete the job (snagging and soffits, fascia and guttering) you, without any conversation, refused to let us do it and said you were finishing the job yourself. Again, typical of your unreasonable behaviour.
 
I left a message saying no more and his reply was to have a lady (secretary?) call me, and then send some workmen round in the morning. He only reacted directly to it when I followed that message up in writing.. and that was in the form of a blackmailing message.

I did note the "to complete the job" and "snagging" words as completing the job was quite a considerable task (note I've had 2 guys on it for 3 weeks now), and that he hadn't contacted me, nor had he independently inspected the work to get a snagging list!

 

 
  I have taken advice and respect your wishes in order to show my reasonableness. The scaffold is being removed today. Strange how he decides to suddenly change his mind, particularly after his voicemail "I won't remove it"  

I wonder if a) he's had a change of heart, b) realised that the letters mean that I am serious about removing it myself or c) has seen this blog and realises it's about him? 

 

Hmmm...  I'm still veering towards c), but then what about the points above that ignore the fact I have so many pictures documenting the real state and poor quality work? I just don't know.

Is reasonableness a word?

 

 
  I would like a site meeting with you or via correspondence, to bring this matter to a close. Sorry, don't get this bit; he wants a meeting with me, or he wants correspondence? Isn't it one or the other?

 

 
  Please be assured I will be seeking final payment from you through whatever means necessary.

 

"through whatever means necessary"? That sounds like another threat to me.

I've so far incurred 3 times the original time of contract and over £3,000 of additional work to put right the poor workmanship (as required by the building control inspector, not by an opinionated builder) and there's still a fair bit to do - I haven't even got a floor!

 

 
  I look forward to hearing from you shortly. I have to wonder if there's really any point replying, but I suppose there is a necessity to do so in some form.

I don't want to jeopardise anything in my reply so will have a chat with someone who knows first.

 

 
 

Basically I had a good laugh at this. The building inspector's coming round tomorrow so I'll let him have a copy (for reference, his files, mates down the pub, whatever).

Something else is that the letter arrived in the cheapest envelope with handwriting on it that looked like it was a child's and hadn't spelt "London" correctly. The letter was printed on the cheapest paper so that it was smudgy and nasty. Quite different to the sales contract then.

I'm still puzzled with what to make of it. On one hand I think he's seen the blog and on the other, how could he? I'm fairly sure he didn't write it though - the MD's struck me as an intelligent man who's very much in control and this just doesn't sound like him. Perhaps the general gist of it was dictated (fast) to someone else who didn't pay attention at school?

 

   
   

Beautiful!

So, how about some pictures from today?

 

 
     
Firstly, the rest of the main loft has now been insulated

The pipe work coming down from the ceiling into the main house has had extra holes made. It was looking pretty awful before
 
Removing the bathroom floor to make it compliant with the fire protection regulations.  Note the mess underneath...    
 
 
 
Cleared and prepared with wire
What a state! Hardly the position I expected to be on week 12...
 
 

Building control inspector is visiting tomorrow to sign off this work. Then the floorboards will go down.

 

   
 

And one final thing. I did a little digging today and found out he has 5 directorships recorded. Looking at some of those companies, this one has had a name change recently and one other active company he has specialise in .... lofts! Wow, who'd have thought he'd have two companies, running two accounts, two sets of assets and probably employing the same subcontractors. Also of note is that the website has much of the same wording and the mobile number on the site is that of the salesman for this company.

The bit I really like on the site is "[company name] do not send unsupervised contractors into your home. We only use our own qualified craftsmen. Many of our craftsmen have been with us for many years. We employ our own Qualified Carpenters, Plumbers, Bricklayers, Plasterers, Tilers, Painters & Decorators"

Sounds great... but it's all just talk isn't it?

 

 
 

Basically chaps I don't think this is going anywhere.

If I take him to court and win, I don't think the company won't honour the CCJ but will fold with no assets just before as the customer's existing contracts are transferred (probably unknowingly) to another company. If this company's name does become public (through court action)... then they'll change.

I have a feeling this guy, with his swimming pool, stables and flashy car has done this before and will do it again. He's clever and knows what he's doing.. and the law offers him too much protection.

On a brighter, depressing (!) note, maybe they're all the same. I found out today from my neighbour that his brother had a loft extension with the specialist company that we nearly did. They did 8 lofts in the road parallel to ours, all happy customers. Doing this guy's, they ran into a finished / not finished dispute and... left the scaffolding up!

So, my advice at the moment if you're thinking - do it yourself. Architect, QS, the works. "Specialist" to me implies specialist in knowing where to cut the corners. 

 

   

 

Be sure to tune in tomorrow for the next tedious instalment of Pikey's bloody loft extension!  (Hey - at least the writing's better than Eastenders!!)

 

 

16th May - Parry - repost!

I spoke to my solicitor and his advice... let it go.

It will a) add chapters to the soap opera, and b) he will phoenix and I'll never actually get the money.

Said I should respond along the following lines:

  • address each point & explain why it's b*llox
  • tell him I've spent £3,000 so far putting right his sh*t
  • say if he wants to issue proceedings then go ahead, in which case I will counter claim for the £3,000, otherwise bugger off.

Sounds like good advice and I'm going to go with it.

A copy of the letter's below:

   
 

16th May 2007

 

Dear [removed],

 Thank you for your letter dated 14th May.

 I was most surprised by its contents since these points had been addressed in previous (written) communications, however to address them formally I will elaborate:

  

1. Scaffolding

On 30th April, I left a message, and put in writing that I was terminating our contract as there was still much work to be done. On 1st May you left a voice mail threatening that you would not be taking down the scaffolding. On the 10th of May scaffolders came and removed the boarding from the access panels at the front and the rear and removed all safety rails. They did not return.

 I was left with no option to respond to this threat advising I would be removing it and I merely ensured you knew I would be exercising my right to remove your property from my land.

  

2. Ignoring your calls

Mr [removed] I have not refused to communicate with you and have only not returned calls when asked 2 times. Once on 17th April where you wanted me to have a conference call with your employee to tell me he never sold “3-4 weeks” and another on 1st May when you had the communication that I had terminated the contract.

 I have used email as a communication tool more than I am happy with, but I thought it necessary due to the contents of voice conversations being forgotten. Email is a perfectly reasonable tool to use to pass information between us and confirm various details. For example, I confirmed to proceed with the contract on email in February.

  

3. Time

Time is and always has been of the essence. Your salesman used the promise of “3-4 weeks” delivery as a major sales point, and even went on to advise how you could manage this with your “no-subcontractor” policy and how you had teams of craftsmen who, it was made to sound, would swarm onto the job to get it done quicker than any others.

 Your website says, and still does, “4-5 weeks”. The contract that I have states “4-5 weeks”.  Even if you think it should be 5-6 weeks, the job is on week 12 and there’s still more to go.

 I am surprised that you state no guaranteed completion date was given, as it was. Firstly, even if I misheard “3-4” (which I did not), the “4-5 weeks” printed clearly implies that 5 weeks from the start (5th March) the work would be finished. Secondly, I asked for repeatedly for dates from both Jason and yourself. After no action I agreed a fair and reasonable date to complete all the works (20th April) and put this in writing. I also discussed this with you on your visit to my house on 10th April. When you had done nothing after a further week, I wrote to you and advised I would be sticking to this deadline. You replied in writing that it would all be done that week (providing a schedule) and said it might slip by a day.

 Since that point, it slipped by 3 days, and then another 2 finally to find that actually there were about 3 weeks left.

  

4. Plumbing

Your comments about the plumber are misinformed. The plumber who came for 1st fix did not return. Another plumber returned who (despite the family emergency that I know about) could not find the hot/cold feeds nor the radiator pickups. A 3rd plumber attended on that Friday, but he merely connected up the hot/cold feed and then left.

 Whilst on the plumbing subject you should know that this 3rd plumber cut and threw away 2 large sections of carpet, left floorboards lifted out, and left a considerable amount of rubble around the area he routed the pipes. In addition, the main and secondary radiator pipes leaked when pressure tested, the shower waste pipe ran uphill and the towel rail was installed with the bottom on the floor. 

  

5. The fireproof insulation on the floor

I am aware that the building inspector has spoken to you about this on the 8th May, so yet again I am surprised.

Firstly, it’s the building inspector’s opinion that matters, not mine. However, when you attended on 10th April, intimidating me over an additional cost of £400 of floorboards if you removed all, you cut a hole in one section of one floorboard that happened to be one of the few with insulation beneath.

 When the inspector attended he insisted that 4 random boards were completely lifted. This revealed that there was only 3 areas that had been done – 1 near the double doors and 2 strips near the veluxes. The inspector subsequently insisted that every floorboard was removed so he could inspect all.

As you can see from this picture showing 50% of the structure’s floor, removing the floorboards showed a great deal of insulation missing.

 Incidentally, removing the floorboards has also uncovered other areas of deficiency in the side supports that has had to be corrected.

 

6. Windows/doors

The most important thing is we have the windows that we want, and the building inspector has allowed them to remain. However your statement saying that I spoke to Jason and changed these doors to windows which were on the drawing is bizarre. 

 The day we saw the plans we highlighted the error and were told that the architect would return on March 8th, 9th and 12th, but never did. You will also note that the contract states what we asked for (and what we’ve got) "One UPVC window 1100m x 1250mm will be fitted to the top of the staircase, and a set of 4 panel French Doors with Juliette balcony to the bedroom.".

 

7. The balcony

The building inspector has ruled the balcony is not compliant and had to be changed or modified. 

This has now been done.

 

8. The bulkhead

The new landing bulkhead is what I wanted amending to look “reasonable”. The bulkhead on the new bathroom floor is what the inspector is referring to.

 As he explained to you during your conversation with him on the 8th May, it needs to be 2.0 and 1.85 will not suffice. 

This has now been done.

  

9. My new contractors

You ask why I didn’t give the contract to Pete? That’s because he said he would take 10 – 12 weeks and your salesman 3-4.

 The 2 main reasons I singled your firm out from the others and decided to go with your company are the speed and the lack of subcontractors used (confirmed in writing on your website)

 

 Finally

To conclude, when I advised the contract was terminated I had an estimate of 2 weeks remaining work, however the new contractors have uncovered more corners cut and work that needed re-doing. The state of the job on the 30th April was quite disgusting and even now, 3 weeks on there is still more to do.

 Acknowledging there is a £2,000 balance on the account, so far I have spent £3,000  in a) correcting the work that was done incorrectly, and b) completing the work that was not done. These are not opinions of a rival builder, these are requirements from the building control inspector, and are itemised and documented, with photographs. The work is not yet finished and this bill will rise.

 I note the threatening nature of your recent communications, and your instance to obtain payment by whatever means necessary.  If you wish to issue proceedings, then I am able to accept service of your legal papers. Otherwise there should be no further communication from this point.

 Sincerely

 

 

I also left a copy out for the building control inspector due tomorrow.

That's it for tonight as I've been on the sauce!!

 

17th May - Nope wasn't me!

 

The building inspector came round, signed off the various items and picked up the copy of the 14th May letter from the loft company (click)

 

   
   

Being particularly vexed at the "building inspector has signed it off" line, he called the company and spoke to the MD.

A rather bizarre conversation ensued in which the MD said that the floor was signed off and he would provide dates of when the inspector came round to sign the floor off by the end of the day (which never materialised).

Amongst other things, he suggested that the client had guys working in the house at the same time as his and whoever messed various things up (ie. the floor) weren't guys working for him. Being told that they were there whilst he (the building inspector) and the project manager was and that the guys were clearly working for the project manager brought us to the rather convenient dead end of pointing out the project manager's not working for the firm any more so we can't ask him.

 

 
 

Right, so whilst I was paying him a shed-load of money and when the contract wasn't in dispute, I was employing other workers to be in the house and mess things up?

Incredible. Just incredible....

 

   

Some pics:

A picture of the stairs (someone asked to see)
The water pipes
 
Bathroom floor insulation
Front 40% of the loft floor with insulation
 
Been inspected by the inspector and the new floor goes back down


All doors in the house now have closers.


 

 

  • Floor and trimmings fully down by tomorrow.
  • Bathroom completed next week
  • Electrical fixes ('cos it wasn't done properly) towards the end of next week.

Then to choose a colour scheme. I'd better get in there first before she goes all Laura Ashley on me :)


 

18th May - A floor that doesn't creak, flex or move

Floor's down and it's starting to look closer to a finish





After spending £130 on an technician to make the airconditioner work, the bloody thing ran out of coolant again. Hmmm.. so, perhaps I didn't put it up wrong, the unit was faulty and I didn't need to pay the company's technical bloke £130!!

This could be a problem - one can't get to the outside without the scaffolding now. Oh joy of joys......

 


Towel rail back on the wall, at a sensible height, with the pipes channelled in, and the electrical wand attached this time.

A man from Sky came and made it work. Seems the receiver thingy in the middle of the dish was faulty.

The new floor is totally different to the previous one that was thrown away. I realised I 'assumed' that cutting up the floor 20 times was normal because, well they're the experts....
 

Stig... happy now? :)

Finally things appear to be on the right path and I can see an end.

Shame about the air con though... seems that every day there's a "something" to challenge me.

 

Week 12   21/05/07 - 27/05/07
8 weeks over

 

21st May - Getting boring now :)

A few people have helpfully suggested a cheaper way to get to the air con system without scaffolding.

The problem is the alley way is too narrow. However, with a scissor lift it should be possible...

But to hire one from www.hss.co.uk for 2 days costs £325.00, where as a 8.2m alley scaff tower for 2 days would only cost £156.00... so as much fun as it looks, I think I'm going to have to stick with scaffolding.

 
Floor's down in the bathroom (the non-wobbly kind, suitable for heated tiles) and had a the seal painted on as well.

A little bit of luxury...
 
 

 

 

22nd May

The pipes the loft company embedded in the wall are leaking.

Some of the floor down and the heated floor is wired and in (only on the small bit one's feet will go!)

 

 

26th May - The floor is down and the shower is in

The shower is finally in. To keep the glass safe, it's been living in my lounge and dining room for the last 2 months, to to have it out and actually installed is a good thing.








All the floor has been completed, the electric heating installed and it's all dry. Very nice.

Unfortunately we're wondering about the toilet and sink that we chose. Looked good at the time, but now, perhaps a little too trendy? We've been looking at magazines to try and find colours that will make it look less... "odd"  :)

Note the position of the toilet on the floor is where it will actually stay. If it's pushed any further back you couldn't use it (unless you were 3 foot tall!). To the rear of it we will be building a box which will have a door and shelves for towels "and stuff".

 
I'm happy with the result. It's a high quality enclosure and really looks and feels it. A few years ago we bought a whole bathroom from B&Q for £270.. and it showed (getting ripped out 6 months later!). Never again - quality components really make a difference :)


The back of the shower is an 'Aquaboard', a laminated, waterproof board that'll look the same as the day it goes in for ever. Tiles are very nice, but eventually the grout gets a bit dirty and it loses it's sparkle. This stuff, which we have in another bathroom is excellent. Also, installed properly it's leakproof.



The shower itself is a high quality brass one, so shouldn't break! It gets its power from a high capacity Worcester Bosh combination condenser boiler downstairs (recently installed). We previously had a cylinder boiler system with a pump, but the pump kept breaking, her ladyship would have a knack of empting the water and it never properly heated the house. Going for a quality product means the whole house can be heated and it can run 2 showers simultaneously. Well... theoretically, anyway! It can certainly run one shower extremely well and with some more taps on appears to cope. It's a lot to ask from a single boiler, but we really wanted the space back from the cylinder and you can't put a pump on a combi feed.

The other thing is the new boiler hugs trees. Something like 70% more efficient than the one it replaced.

 
This is a shot of the flooring, which is just SO MUCH BETTER than the completely cut up, wobbly, creaky mess that was there before. Makes me wonder why they put the floor on first. Surely it should only be permanently fixed once everything underneath has been done???
   

After many calls, the air conditioning company's technician called me back. He's going to pop round to see how he might get up there, which is fine but I said that I don't see the point of re-filling this unit up with gas when there's clearly a fault. I want a new unit...  He's having a look and then will call the office to see what we can do.

I think there'll be some compromise here and I'm prepared to go to: they send a new unit, I pay for scaffolding, they put the replacement one in, the old unit goes back to them.

We'll see.
 

   

To quote the MD of the outed loft company.... "almost there" :)

 

 

 Week 13  28/05/07 - 03/06/07
9 weeks over

 

So you're probably wondering why nothing's happened, well I've lost my builder.

Progress has been slow due to the attendance has been pretty poor, but after 5 days of no attendance (and not answering his phone) I went round to his house to ask what's going on.

The answer was he's on another job, a neighbour's kitchen, "be finished in another week" he said.

Nice that he told us rather than just disappear isn't it.... 

In the meantime we popped a few coats of paint around the place. Keeps the plaster dust at bay!
 

   

 

 Week 14   04/06/07 - 10/06/07
10 weeks over

 

7th June - An update at last!

The building inspector came round yesterday and signed everything off apart from the toilet (as it wasn't fully operational). Once this is done and tested, he'll issue the cert.

 
   
It's looking quite nice - not cramped or pokey

Behind the toilet will be a cupboard for storage. The nasty stuff will be hidden in it's own box.

 

 
Looks nice.
 


This is odd. As well as having door closers on EVERY door in the house, this glass panel door from the hallway area to the utility room & kitchen had to be changed to a fire door.

 

 

 

 Week 15   11/06/07 - 17/06/07
11 weeks over

 

11th June


The stairwell landing lights being moved to a reasonable position.
 
Bathroom's looking better with skirting board in and cupboard built. Also the toilet now flushes and all the plumbing has been completed.


 
As people have asked:

The shower unit is not a five jet but a four or a one jet (as we were told by the salesman). In the four body jet mode it's just about powerful enough to be usable....



.. in the one jet mode for the head, it's quite powerful enough!
 

 

 

Page 7 here

 


Wanna get in touch? contact@myloftextension.co.uk


www.myloftextension.co.uk