| Page 7
here
(previous page here) |
|||
| Week 33 15th September to 21st September | |||
| 15th September | |||
| On
our return we were (naively!) stunned to find he had done very little. What was done was electrical 2nd fix plus what can be seen here: patio's base had been installed (with drain) and a scratchcoat on walls. |
|||
|
|
|||
| 16th
September We sought external advice and I was advised that working out a way forward with this builder would still be quicker way to completion than terminating the contract. We spoke to the builder who apologised repeatedly, but wouldn't give a reason why he hadn't done it. He did stress that he wanted to complete the work if we would give him another chance. We set out a way forward; he listed items that were remaining and set an hourly rate against each. From this it appeared 190 hours were required to complete. He assured me him and the others would work 8 hours a day. 3 guys, 24 hours work per day, 190 hours of outstanding, 8 days (bar snagging). Reasonable... but despite his assurances I was sure he wasn't going to do 8 hours per guy per day as he didn't acknowledge how the frequent stoppages (tea breaks) affected this time. I would keep a log of attendance and stoppages from this point.
19th September Assuming he would have completed, my parents in law rearranged many things to come down this weekend, with our "puppy" they'd been looking after. The same puppy that went away five months away for a month and wasn't much of a puppy anymore.
|
|||
The main wall's been
painted![]() |
Now the place
can be kept dust-free, and we have visitors, we bought a
sofa from this rather aptly named company.
Superb sofa actually. Would highly recommend them :) ![]() |
||
It finally
seems to be making the transition from "building site" back to "home"!![]() |
Sunny.... ![]() |
||
Maximillion
the wonder dog returns, considerably bigger after half his life of
country living chasing foxes.![]() |
|||
| 21st September At the end of this week, according to the builder's calculations he should have worked 120 hours, but the reality was 58, equating to 7.8 mandays lost. I tried to speak to him about this and explain that as he's paying his workers a day rate this is additional money he's paying needlessly, but didn't get far as he assured me he would reach the end as agreed.
|
|||
| Week 34 22nd September to 28th September | |||
|
Progress this week: |
|||
Benches created |
|
||
Example of rainwater build up on top of the
roof lights. There's simply no drainage at all.![]() |
![]() |
||
Benches
screeded![]() |
Steps made![]() |
||
| A new table!
Bought from a fantastic chap, made to my requirements for a very
reasonable price and delivered in a short time. Superb.
Chunky
Furniture the company is called. |
Shame about
the forced dog leg reducing the amount of space here, but it still feels
spacious and works fairly well |
||
|
I addressed the ridiculously easy (and well known) burglar entry point by changing the lock barrel for a modified one. The lock on the top is the
replacement and on the bottom is the supplied. The supplied lock's
design flaw is having a single weakpoint (the securing hole in the
middle) which will fail when lateral forces are placed upon it, whereas
the replacement one has two additional weakpoints (in red). Of course this doesn't make the house burglar-proof, but does remove their ability to spend 10 seconds on forcing entry before calmly opening the door and walking in. You would have thought that the door company would have added £20 to the cost of their £3,700 doors with lots of security to address this...
|
|||
|
28th September So the end of this week has the builder done the 120 hours he says they would? Nope. This week they did 73 which is 5.8 mandays lost. This included all 3 of them leaving at 2pm on Tuesday "to get the fence panels" and a surprising late finish on Thursday of 5pm. No fence panels ever arrived on site this week. I did find out that he day rate he pays his guys is £180. So that's £1,400 last week and £1,000 this of wasted labour. I hope for his sake that he's at least working somewhere else as well. |
|||
| Week 35 29th September to 5th October | |||
29th September I spoke to the builder again to express my concern of how few items of the list he had completed. I tried to explain about the days lost last week and the one before, and if he had the guys working 8 hours a day we would already be finished. He assured me not my concern and he would be finished in a few days.
1st October When I got hold of him he cited poor weather and disagreed it was good enough to work. These pictures were emailed to him at 10am prove the weather was ok, but I was unable to get him back on the phone. |
|||
![]() |
![]() |
||
|
The following day they turned up half a day late.. but assured me "they
weren't on another job, honest".. Further work this week: |
|||
Roofing
finished![]() |
Drain
finished![]() |
||
Guttering
installed![]() |
|||
|
4th
October 2 hours later, I was told the van had broken and he'd still be coming back. 2 hours after, the van was being towed somewhere to be fixed, but would be ready tomorrow. Today I he said he was coming round "in an hour"... and then no answer on his phone for many more. I called his house to find him there and asked him to come round to talk. He did and would only say he promised to be finished by Wednesday.. Not that it's relevant, but this week the score is 9 mandays lost |
|||
| Week 36 6th October to 12th October | |||
Majority of tiling completed ![]() |
![]() |
||
| Level of
inner and outer floor is as good as the design with it's level with the sill being a neat,
submerged track. Unfortunately
the grout left over the tiles appears near impossible to shift. |
|||
|
Flew past the "by Wednesday" promise on Saturday without a whisper. Hours this week were much of the same, with little progress shown. 6.7 days lost. Too much outstanding. Out of the items that had been done they'd managed to generate more snagging issues. Very unhappy. |
|||
| Week 37 13th October to 18th October | |||
The
"van-full" of turf that was stuck in the broken down 2 Friday's ago
didn't appear but these 6 strips did. ![]() |
Fences![]() |
||
I brought the
garden furniture down into the patio area![]() |
The space seems to work
well![]() |
||
| 17th
October This week they were here for a few hours on Monday and a few on Tuesday.
|
|||
| Contract end | |||
| Page 7
here
(previous page here) |