Page 4 here  
(previous page here)
     
Week 14  5th May to 11th May
       
8th May      
All foundations laid. Base brickwork started. Lintels over pipes.
 
     

 

   
Week 15  12th May to 18th May
       
13th May      
   
   
       
17th May      
   
   
Pipe covering void filled with shingle
Most of the kitchen removed
   
Utility room removed
Temporary kitchen / utility room
   
       
     
Week 16  19th May to 25th May
       
23rd May

Today was supposed to be the finish date, but with 8 weeks of water board delay, a new date is needed.

The builder provided a revised project plan showing the tasks from now until the project's completion and the end date of 18th July, advising that is the worst case date, it has fat in it and he actually hopes to finish a week or more before this.

It's a bit close to our wedding for our liking, but this water board thing wasn't foreseen and as long as it's done before the wedding we don't mind that much.


 

   
Doors arrived. This is 3 of 4 panels.

   
Kitchen now stripped of floor, old pipework and electrics
The new floor level makes the room feel a lot taller
   
View to utility room
Blockwork completed
   


The height of the wall needed was 100mm higher than the architect had stipulated on his drawing
   
Foundations laid for the upright steels to support the main supporting steel
And the other end, inside the existing kitchen
   
     
Week 17  26th May to 1st June
1st June

Builders did not show up this week, citing poor weather as the reason.
     
     
Week 18  2nd June to 8th June
       
4th June
 
     
Steel girders arrived. These monsters are the main ones spanning the whole length of the extension.

Moving them to the back was difficult. They say they're going to put them in with "lots of people".
   
The final resting place for them. You'll note it's quite high, as well as long.


This girder supports the horizontal ones (will go in place of the wall to the right of the boiler). Note that being propped up it seems to be too tall - it isn't, they have to dig a hole in the ground to slide it in.
   
Before they can do that though, they need to insert this large padstone. The one on the right, goes on the inside half on my wall, half on the party wall inside the house and the one on the left is on the new extension wall.
They start to remove the outside wall.


   
With the reduction from the walls coming down, the inner door has been replaced with a steel security door
Digging to find the drain (requires a spur into it from the new toilet) ... 7 feet down!
   
Skip number 17 arrives

     
       
     
Week 19 9th June to 15th June
       
11th June
 
     
Installing the main steel girder
   
Once on top, it's then slid into position
Being bricked into place
   
Supports inside the kitchen holding the house up. These will remain until the cement around the new bricks has set
   
       
13th June
 
     

All of the girders are in place, bolted and welded
   
Note the joists have bowed over the years. They'll need to be packed out to stop the tiles on the bathroom above cracking.
This should be the last shot of this wall as it's about to go. I guess we'll then find whether or not the girders will actually hold the house up!
   
       
18th June
 
     

All the walls are now down and it looks like the steel girders are holding the house up

   


 

   

   

Horizontal RSJ onto vertical RSJ and padstone                           Oh, and yes the toilet is still connected!

 

 

   
       

 

     
Page 4 here  
(previous page here)
     

 

Extension blog front page

 

www.PikeyNet.com