Build Diary

 

  Week 1 Making a hole
  Week 2 Making a big hole
  Week 3 Making a really big hole
  Week 4 Digging foundation trenches
  Week 5 No movement. Delayed due to cold weather and lack of water board decision
  Week 6 No movement. Waiting on water board decision. Specc'd a kitchen
  Week 7 No movement. Water board advise incorrect application
  Week 8 No movement. Water board advise common drain is too near extension wall
  Week 9 No movement. Water board finally approve application
  Week 10 No movement. Water board decide application is not approved
  Week 11 No movement, but Water board decide perhaps it is ok after all
  Week 12 No movement - more drawings needed
  Week 13 Foundations laid
  Week 14 Walls up. One steel girder in
23/05 Week 15  Kitchen / Lobby cleared. Pipework cables out. Blockwork finished
30/05 Week 16 No movement, weather prevented work
06/06 Week 17 Steels prep work complete. Drainage bypassed. Groundwork ready. Roof preps. Electrics carcussed. Manhole in. Steel girders on site.
13/06 Week 18  Steel girders in. Areas of walls down.
20/06 Week 19 Form roof works. Remaining walls down. Kitchen delivered
27/06 Week 20  Roof up. Plastering / Rendering started.
04/07 Week 21  Floors started. Rendering finished
11/07 Week 22  New studwork started. Kitchen complete. Floor tiling / wall tiling. Drcs started. Shower room fittings. Breaking into lounge & doors fitted. Walls finished. Kitchen installation start. Garden walls commence.  Internal floors. Electrics 1st fix. Plumber 1st fix. Underfloor heating. Screed commence. Doors fitted. Ceilings in.
18/07 Week 23 Garden works / back fills / floors / etc. Internal works / Drcs complete. Carpentry works completed. Site tidy work started.
25/07 Week 24 Snag works undertaken. 2nd fix all items/ Site cleaning and finalising works.
01/08 Week 25  
04/08 Week 26  
11/08 Week 27  
18/08 Week 28  
  Week 29  
  Week 30  
     